Notification under Tamil Nadu Country Planning Act, 1971(dated-02.01.2023)-Govt. of Tamil Nadu.
View PdfNotification under Tamil Nadu Country Planning Act, 1971(dated-02.01.2023)-Govt. of Tamil Nadu.
- The minimum distance to be maintained between the Wind Electricity Generator (WEG) and Public roads /Railway tracks / Highways / High Voltage electric lines/ Buildings / Public Institutions shall be the height of the tower/hub height (in metre) + Half the diameter of the blade/Rotor (in metre) + 5 metres.”;
- Wind Electricity Generator (WEG) shall not be erected within 500 metre from any dwelling unit.”
- The plan showing the micro siting of Wind Electricity Generator (WEG) within a site and their specifications regarding development, installation, erection and operation shall be certified by the Tamil Nadu Generation and Distribution Corporation Limited”., – refer attachment for further details.