Guidelines for Field Efficiency Test in Hydropower (dated- 20.06.2023) – Central Electricity Authority

  • 07th, July 2023
  • compfie_wp
  • Comments (0)
View Pdf

– Guidelines for Field Efficiency Test in Hydropower (dated- 20.06.2023) – Central Electricity Authority.

  • The Central Electricity Authority has issued a guideline for Field Efficiency Tests in Hydropower Plants (including Pumped Storage Projects). The guidelines will be applicable to any size and type of unit comprising a generator- motor and impulse/ reaction turbine, and pump-turbine above the unit size of 5MW, please refer attachment for further details.